Construction Timeline

The reconstruction of the building is divided in to two phases. These phases will allow a portion of the building to be used as teaching and Research space while the remaining areas are renovated. The phasing process, along with the relocation of the faculty offices to Mooney and Duffy Hall, have enabled the faculty to maintain all teaching and Research functions throughout the course of the project.

Phase I

Timeline May 24, 2005 – August 19, 2006

This phase is the most extensive as it includes the construction of the new addition at the front of the building and a renovation of half the existing structure. Included in this work is all of the major site and infrastructure improvements such as water, sewer, electric and gas and the addition of the fifth floor mechanical penthouse which will house all of the HVAC equipment for the entire project.

Phase II

Timeline - September 1, 2006 – July 15, 2007

Upon the completion of Phase I, the remaining labs in the occupied section of the building will be relocated to the newly constructed labs. Once the faculty and labs are relocated this phase includes the renovation of the remaining portion of the existing building. During this time, the new sections of the building including the conference rooms, classrooms and amphitheater will be open and scheduled for campus use. The faculty offices will remain in Mooney and Duffy Hall until the completion of Phase II.